A Process takes inputs and transforms them into outputs, and may be connected to other Processes in process flows. The work of Training others work contributes to This Process.

A Process happens in an organizational Context.
Context: The Project Building SENSORICA
This process fulfills a Work order.
Order: Work order 241 , GOSH conference event due: 2017-03-25

Previous processes:

This Process:

GOSH conference event starting 2017-03-01 ending 2017-03-25

Input requirements:

Time Contribution Presentation Conference (give) work 1.00 Each
Time Contribution Training self work 1.00 Time - Hours
Time Contribution Facilitation work 1.00 Time - Hours
Time Contribution Documenting 1.00 Time - Hours
Time Contribution Meeting work 1.00 Time - Hours
Time Contribution Information mining work 1.00 Time - Hours
Time Contribution Recruiting work 1.00 Each
Time Contribution Analysis and strategy work 1.00 Time - Hours
Time Contribution Training others work 1.00 Time - Hours
Time Contribution Event organizing work 1.00 Time - Hours
Time Contribution Writing work 1.00 Time - Hours
Time Contribution Infrastructure development work 1.00 Time - Hours
Citation Documentation
Citation Presentation
Citation Brochure

Output plans:

Brochure 1.00 Each
Presentation Conference (give) work 1.00 Each
Presentation 1.00 Idea

Next processes: