A Process takes inputs and transforms them into outputs, and may be connected to other Processes in process flows. The work of Work - Documenting contributes to This Process.

A Process happens in an organizational Context.
Context: The Project Optical soil moisture sensor

Developing optical soil moisture sensors

This process fulfills a Work order.
Order: Work order 235 due: 2016-10-12

Previous processes:

This Process:

Prototypes for Connected Fields starting 2016-09-07 ending 2016-10-12

Input requirements:

Time Contribution Work - Technician experimental 20.00 Time - Hours
Time Contribution Work - Meeting 4.00 Time - Hours
Time Contribution Work - R&D optics 20.00 Time - Hours
Time Contribution Work - R&D electronics 10.00 Time - Hours

Design of the transmitter & receiver circuits.

Time Contribution Work - Documenting 20.00 Time - Hours
Time Contribution Work - Training self 20.00 Time - Hours

Research readings.

Output plans:

Next processes: