Process: Get contracts to build fablabs in schools starting 2015-08-22 ending 2015-08-22

If you were logged in and working on this process, you would log your work on this page.

Outputs

Scheduled:

Presentation 1.00 Idea due Aug. 22, 2015
Brochure 1.00 Each due Aug. 22, 2015
Video 1.00 Idea due Aug. 22, 2015

Work

Planned Work: (Requirements are ordered by due date)

Work - Accounting and Finance: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Training self: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Administration: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Artistic: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Training others: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Customer service: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Manual: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Documenting: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Information mining: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Office: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Business building: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Transportation: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Infrastructure development: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Outreach-Marketing: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Facilitation and coordination: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Meeting: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Demo: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Shopping: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Recruiting: 1.00 Each due Aug. 22, 2015
Unassigned
Work - Writing: 1.00 Time - Hours due Aug. 22, 2015
Unassigned
Work - Analysis and Strategy: 0.00 Time - Hours due Aug. 22, 2015

- Defining the specifications of a FabLab
- Defining the procedure required to setup a FabLab

Taken by Ahmed
Work events:
Sept. 12, 2015 1.00 Time - Hours Done by Ahmed

- Writing document E_03_FabLab 3D Printer

Sept. 8, 2015 1.00 Time - Hours Done by Ahmed

Writing the document E_02_FabLab CNC Machine

Sept. 7, 2015 4.00 Time - Hours Done by Ahmed

- Writing the document E_01_FabLAB Laser Cutter
- Writing the document I_03_Documents Tree

Sept. 6, 2015 3.00 Time - Hours Done by Ahmed

Gathering information about existing FabLabs

Aug. 22, 2015 2.00 Time - Hours Done by Ahmed

- Writing the main topics of the "FabLAB Initiation Document"
- Basic list of available CEGEP

Consumable Inputs

Office Space: 1.00 Area - square meters due Aug. 22, 2015
Work - Design website: 1.00 Each due Aug. 22, 2015

Usable Inputs

Sound system: 1.00 Each due Aug. 22, 2015
Equipment - Camera photo/video: 1.00 Each due Aug. 22, 2015
Onhand: HP webcam 1.00 Each
Onhand: Logitech HD webcam 1 1.00 Each
Onhand: Logitech low def. 1.00 Each
Onhand: Phil's CCD 1.00 Each
Onhand: Video camera 99%media 2.00 Each

Process context:

Pattern: Funding initiative
Context: FabMobile
Order: Work order 174 , Get contracts to build fablabs in schools due: 2015-08-22

Previous processes:

Next processes: