Process: Milestone 1 Write report to Conditions for PV characterization starting 2015-06-30 ending 2015-07-02

If you were logged in and working on this process, you would log your work on this page.

Outputs

Scheduled:

Document - Conditions for project @Outreach for resources 1.00 Idea due June 27, 2015

Work

Planned Work: (Requirements are ordered by due date)

Work - Documenting: 6.00 Time - Hours due May 30, 2015

Write a report for Mileston 1 with others

Taken by Jim
Work events:
July 3, 2015 3.00 Time - Hours Done by Jim
Work - Documenting: 4.00 Time - Hours due May 30, 2015

Create a comprehensive report to close Milestone 1.
This report will be used in Milestone 2, to inform the Design phase.
The report should be sent to Joshua Pearce from Queen's University at the end of this milestone.
See more on the description on the right.

Taken by Tammy
Work - Documenting: 8.00 Time - Hours due May 30, 2015

Write the Report for Milestone 1 with others.

Taken by Tibi
Work events:
June 4, 2015 8.00 Time - Hours Done by Tibi

Report writing, practically the whole night with Jim and Bruce.

Unplanned Work:

Work event: Document - Documentation 2.00 Time - Hours July 3, 2015 Done by Tammy

With Tibi, Jim and Abran, final final edits on Milestone 1 Report.

Work event: Document - Documentation 1.00 Time - Hours July 2, 2015 Done by Tammy

Final edits through technical document.

Work event: Document - Documentation 6.00 Time - Hours July 2, 2015 Done by Jim

Worked with Tammy, Abran and Tibi on the report document

Work event: Work - Documenting 6.00 Time - Hours July 1, 2015 Done by Tibi

Worked with Tammy, Jim and Abran, on working on the Report document.

Work event: Document - Documentation 2.00 Time - Hours July 1, 2015 Done by Jim

Worked with Tammy, Abran and Tibi on the report document

Work event: Document - Documentation 4.00 Time - Hours July 1, 2015 Done by Tammy

Witness: Tibi

Proofreading and editing the document - wordsmithing. Provided feedback and ideas of how the document was presenting.

Process context:

Pattern: Documentation
Context: PV characterization
Order: Work order 165 for Conditions for PV characterization due: 2015-08-22

Previous processes:

Create structure to Conditions for PV characterization starting 2015-05-14 ending 2015-06-19

Next processes:

Milestone 2 Outreach to Conditions for PV characterization starting 2015-07-03 ending 2015-07-17


Process notes:

Close Milestone 1 with a comprehensive report.
Budget allocation: $100.00, for 4 full hours, at 25$/hour.
You can claim the extra time as equity for the commercial version of the device.

See budget allocation
https://docs.google.com/spreadsheets/d/1WtMcgn96mZZbb8nZ14ywIjrIZ6MPW5pc8zmueae0IqY/pubhtml#

NOTE: If you take the task on the left, you can invite a collaborator to it.