Process: Mapping existing technology to Create conditions for the Piezo Buzzer project starting 2014-10-31 ending 2014-11-03

If you were logged in and working on this process, you would log your work on this page.

Outputs

Scheduled:

Document - Conditions for project @Mapping existing technology 1.00 Idea due Nov. 3, 2014

Work

Planned Work: (Requirements are ordered by due date)

Work - Information mining: 15.00 Time - Hours due Oct. 31, 2014

Create a list of existing technology

The goal here is to avoid reinventing the wheel as much as possible and to speed up innovation. The accent is put on open source technologies that can be remixed.

Use some tool for gathering information about all existing technologies that can be applied in this project. You can use Diigo https://groups.diigo.com/group/sensorica-knowledge or simply a spreadsheet. If you use Diigo, create a tag specific to this search, to make it easier for others to find/filter the data.

Place the information in categories, as mechanical, electronics, optics, attributes or functions, etc.

This material will be used later to make a decision about what to integrate and how much to build on top of existing technologies.

Unassigned

Process context:

Pattern: Change
Context: SENSORICA
Order: Work order 144 for Create conditions for the Piezo Buzzer project due: 2014-11-23

Previous processes:

Outreach for resources to Create conditions for the Piezo Buzzer project starting 2014-10-31 ending 2014-10-31

Next processes:

Benchmarking to Create conditions for the Piezo Buzzer project starting 2014-11-03 ending 2014-11-06


Process notes:

What is already out there. The goal is to integrate open source innovation as much as possible, avoid reinventing the wheel, go for fast innovation.
Map open source communities and their offers.