Process: Piezo Actuator Design 3 ax (stack+tube) V2 - for the Mosquito and Piezo Actuator - Design - Mechanical starting 2013-06-01 ending 2013-07-01

If you were logged in and working on this process, you would log your work on this page.

Outputs

Scheduled:

Design Mechanical - Manipulator actuator 1.00 Idea due July 1, 2013

Work

Planned Work: (Requirements are ordered by due date)

Unplanned Work:

Work event: Work - Design mechanical 20.00 Time - Hours June 19, 2013 Done by Daniel

https://docs.google.com/document/d/1I5BPWf6O2QR9VRS-u3yF4WT9v0RuHnIVheRrNzASoxI/edit#heading=h.64lkzf17pd4r

An improved version of the Actuator 3 ax V1 (stack+tube) - for the Mosquito