Process: Detailed planning for Verdun project starting 2017-11-07 ending 2017-12-31

If you were logged in and working on this process, you would log your work on this page.

Outputs

Scheduled:

Work

Planned Work: (Requirements are ordered by due date)

Unplanned Work:

Work event: Work - Meeting 1.50 Time - Hours March 28, 2018 Done by Tibi

Worked with Eiman, an urban designer and planner on the Verdun project. She is going to help with choosing a space and with our negotiations with the Ville de Verdun.
Provided some training.

Process context:

Pattern: Documentation
Context: Verdun

Previous processes:

Next processes:


Process notes:

Collaborate with your peers that are most knowledgeable about the Verdun project to produce a detailed planning of this 5 years project.

The working document is here
https://docs.google.com/document/d/1_fnZ-YMiM1VYEhtwoLpjtjKvEtnAHnMljqqIOuG4I-k/edit

Coordinate with Tibi (SENSORICA) and Alex (OuiShare)