Date Type From Project Resource Type Qty URL Description Process Deliverables
Jan. 15, 2019 Time Contribution Tibi CourseEntrepreneurship Work - Writing 0.60 HR Completed the main coordination document. Wrote a text for outreach. Set up course for collaborative entrepreneurship and Product service and Product service
Jan. 15, 2019 Time Contribution Tibi LED green wall Work - Documenting 1.00 HR Worked on the design doc: design considerations and design features for electronics, mechanics and software. Share it with the community. Green Wall prototype for the Sensorica lab Design: Green Wall design - Sensorica lab prototype
Jan. 11, 2019 Time Contribution Bruce LED green wall Work - R&D mechanics 3.00 HR Worked with Tibi at the Sensorica lab on design consideration of the green wall. Green Wall prototype for the Sensorica lab Design: Green Wall design - Sensorica lab prototype
Jan. 11, 2019 Receive Bruce Building SENSORICA Currency - Canadian Dollars 7.60 CAD
Jan. 11, 2019 Time Contribution Tibi LED green wall Work - Shopping 1.50 HR Went with Bruce to Home Depot to identify parts for the green wall, after design session. Green Wall prototype for the Sensorica lab Design: Green Wall design - Sensorica lab prototype
Jan. 11, 2019 Time Contribution Tibi Building SENSORICA Work - Accounting and Finance 0.50 HR Went to the bank to deposit the cash, and logging.
Jan. 11, 2019 Time Contribution Tibi LED green wall Work - R&D mechanics 3.00 HR Worked with Bruce at the Sensorica lab on design consideration of the green wall. Green Wall prototype for the Sensorica lab Design: Green Wall design - Sensorica lab prototype
Jan. 11, 2019 Time Contribution Bruce LED green wall Work - Shopping 1.50 HR Went with Tibi to Home Depot to identify parts for the green wall, after design session. Green Wall prototype for the Sensorica lab Design: Green Wall design - Sensorica lab prototype
Jan. 11, 2019 Receive Tibi Building SENSORICA Currency - Canadian Dollars 500.00 CAD
Jan. 8, 2019 Receive Tibi Infrastructure-physical Currency - Canadian Dollars 11.00 CAD Went to the store to Purchased brackets and electrical wire for the lab.
Jan. 8, 2019 Time Contribution Tibi Infrastructure-physical Work - Shopping 0.20 HR Went to the store to Purchased brackets and electrical wire for the lab.
Jan. 7, 2019 Time Contribution Tibi Building SENSORICA Work - Accounting and Finance 2.00 HR More communication and coordination with sensoricans. Announced the Education for collaborative entrepreneurship initiative.
Jan. 7, 2019 Time Contribution Tibi Building SENSORICA Work - Administration 2.00 HR General communication on sensorica mailing list, and lined up a few initiatives to be rolled out in sequence
Dec. 20, 2018 Time Contribution Tibi Building SENSORICA Work - Shopping 0.10 HR went to the shop to make keys and to the store to buy paper.
Dec. 20, 2018 Receive Tibi Building SENSORICA Currency - Canadian Dollars 5.75 CAD
Dec. 18, 2018 Time Contribution Tibi OpenRUGDMMAC Work - Administration 0.75 HR Open worked on the project page, communicated to the community and to Anthony about next steps.
Dec. 15, 2018 Time Contribution Tibi Building SENSORICA Work - Administration 0.10 HR Went to the back to make a deposit.
Dec. 15, 2018 Receive Tibi Building SENSORICA Currency - Canadian Dollars 731.00 CAD Tibi deposited 731$ to CAKE's account to pay the rent for the Sensorica lab for February. This was done in a 1000$ deposit, which contained 269$ that represented 5% of Tibi's gains during eco2FEST 2018 (announced to the network on the main mailing list)
Dec. 8, 2018 Receive Tibi Building SENSORICA Currency - Canadian Dollars 8.63 CAD
Dec. 3, 2018 Receive Tibi Building SENSORICA Currency - Canadian Dollars 322.32 CAD SignalSpace (SpiderRig project sponsor) made an eTransfer to Tibi for the entire amount. Tibi had to deposit 80.58$ to pay Alejandro and Mohammad by Paypal, + 90.05 to pay the 5%. See details in payment. https://docs.google.com/spreadsheets/d/1KhbHLt0q1nOvdaPNNDyFkDN-yOGnBKQMQIp5b3vvAvc/edit#gid=54634833 But Tibi deposited in all 500$ cash. And Tibi had to pay another 5% of 7.05$ from 150$ check from INRS, for a presentation. The rest 322.32$ is for Tibi as an investment in Building Sensorica.
Dec. 3, 2018 Time Contribution Tibi Building SENSORICA Work - Accounting and Finance 0.50 HR Open downloaded bank account statements from 2017 and 2018 from CAKE's account, and uploaded them into the CAKE's account statements folder, to be publicly presented on CAKE's website. Had to rename and rearrange all these statements.
Dec. 3, 2018 Receive Tibi Building SENSORICA Currency - Canadian Dollars 1000.00 CAD Invested 1000$ in Sensorica as a contribution to pay rent. Deposited 1000$ cash into CAKE's bank account.
Dec. 3, 2018 Time Contribution Tibi Building SENSORICA Work - Accounting and Finance 0.30 HR Went to the bank, make online transfer to pay rent to EVA
Dec. 3, 2018 Give Tibi Infrastructure-physical Currency - Canadian Dollars 10.79 CAD
Nov. 20, 2018 Time Contribution Tibi Building SENSORICA Work - Administration 0.25 HR Answered Contact US requests.